Documentation for GreenHopper 6.2.x. Documentation for other versions of JIRA Agile is available too.
GreenHopper is now called JIRA Agile. Learn more.

(info) Note that this page only applies if you are using the Classic Boards (which are no longer being actively developed; read more).

 

You must have the 'JIRA Administrators' global permission before you can restrict GreenHopper to selected projects.

You can restrict the projects to which GreenHopper is available. If you restrict a project from using GreenHopper, this means that you will not be able to select your project from the Classic Planning Board, Classic Task Board, Classic Chart Board or Classic Released Board. Please note that the 'Agile' dropdown menu will still appear on projects that don't have GreenHopper access, but if you try to view any of the boards they will default to the last project that was viewed on that board.

To restrict GreenHopper to selected projects,

  1. Log in as a user with the 'JIRA Administrators' global permission.
  2. Select JIRA Administration from the top bar, then select Add-ons > GreenHopper.
    OR, if you are using JIRA 6.0 or later, click the 'cog' icon in the top bar, select Add-ons, then scroll down the page to the GreenHopper section.
  3. Select Enabled Projects.
  4. Select Apply to these projects. The Project list and GreenHopper projects select boxes will become enabled.
  5. Move projects between the two select boxes by using the << and >> buttons.
    • Project list — this list contains the projects that do not have GreenHopper access.
    • GreenHopper projects — this list contains the projects that are available within GreenHopper.
  6. Click the Modify button to confirm the projects available to GreenHopper.

Screenshot: Restricting GreenHopper to selected projects