How To Configure Planning Horizon to 30 years (Part of Dark Features) for JIRA Portfolio
Platform notice: Server and Data Center only. This article only applies to Atlassian products on the Server and Data Center platforms.
Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.
*Except Fisheye and Crucible
Problem
The planning horizon has been configured to one default value which is 5 years. However, in Recalculating the schedule, it is mentioned that the planning horizon can be configured to 30 years as well.
Note: Planning horizon can only be configured to 5 OR 30 years only.
Solution
- Login as an administrator and go to [your-instance-name]/secure/SiteDarkFeatures!default.jspa
In the Enable Dark Feature text field add the following and then click on "Add". This will automatically configure the Planning Horizon to 30 years.
com.atlassian.portfolio.scheduling.UnlimitedPlanningHorizon
Note: These dark features are enabled for all users and cannot be disabled other than via this screen.
This will automatically configure the Planning Horizon to 30 years.