Note that this knowledge base article was created for the Data Center version of the product. Data Center knowledge base articles for non-Data Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.
*Except Fisheye and Crucible
Summary
The purpose of this article is to show how to get a list of all the issue status transition from database in JIRA. The status transition can be seen at the "History" tab of the issue. This article will help on getting a list of issue status transition of all issues in past x days in JIRA by executing a SQL command against the JIRA database. This SQL query is an extension of the SQL query from How to List all the Issue Status Transitions from Database in Jira.
Workaround
- Log in to JIRA database.
- Run the following SQL command to list the status transitions:
SELECT changeitem.oldstring, changeitem.newstring, changegroup.author, changegroup.created FROM changeitem JOIN changegroup ON changeitem.groupid=changegroup.id WHERE (changeitem.field='status' AND changegroup.created >= current_date - interval '7 days');
The query will return records for past 7 days.
- Example result will look like following:
oldstring | newstring | author | created
--------------------+--------------------+----------+-----------------------
Open | Review | admin | 2015-05-25 09:27:46+08
Resolved | Closed | admin1 | 2015-05-25 09:51:30+08
Open | Closed | admin | 2015-05-25 09:59:22+08
Investigation | Analysis | admin2 | 2015-05-25 10:44:22+08
Analysis | Consultation | admin | 2015-05-25 10:51:13+08
Open | Resolved | admin | 2015-05-25 10:53:26+08
Resolved | Closed | admin1 | 2015-05-25 10:53:29+08
Change Approval | Change Development | admin | 2015-05-25 11:35:27+08
Open | Review | admin2 | 2015-05-25 12:05:58+08
Open | Resolved | admin | 2015-05-25 12:15:20+08
Resolved | Closed | admin | 2015-05-25 12:15:23+08
...