How to move start and end dates of issues with its dependant issues in the project timeline


Platform Notice: Cloud - This article applies to Atlassian products on the cloud platform.

Summary

When you try to move issues in the project timeline to change the start and end dates you can use the below steps to also move the linked issues in the time along with it. This will prevent dependent issue dates from overlapping, especially when one issue blocks another.


Environment

Jira Cloud


Solution

To move all the linked issue dates at once in the Project timeline,

  1. Select all the timeline bars of the issues in the timeline by using Ctrl/Cmd + left-click on the timeline bar itself.
  2. Once selected, Drag any one of the timeline bars across the timeline.
  3. You will other selected timeline bars move along with this maintaining the same-day difference.
    Test.mp4