Plan shows incorrect start date for sprints on plans

Still need help?

The Atlassian Community is here for you.

Ask the community

robotsnoindex


Platform Notice: Cloud and Data Center - This article applies equally to both cloud and data center platforms.

Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

The Sprint Start Date in plan is showing 1 day prior from the actual start date of the sprint.

Environment

Jira Software cloud

Diagnosis

Check your timezone in Jira. If it is IST timezone and If you have put 12.00 am or 12.30 am IST as your sprint start time.

Considering IST = UTC+ 5.30, the time displayed on plans would be UTC =  IST - 5.30 am, which is shown as previous day.

Cause


As for all dates in Advanced Roadmaps, sprint dates are converted to their UTC (Coordinated Universal Time) equivalent.

Solution

In order to overcome this, the workaround is to select a time for sprint start date as 5.30 am when your timezone is IST hours.




Last modified on Mar 7, 2025

Was this helpful?

Yes
No
Provide feedback about this article
Powered by Confluence and Scroll Viewport.