Remaining hours and Due Date auto populated when linking dependencies

Still need help?

The Atlassian Community is here for you.

Ask the community

Platform notice: Server and Data Center only. This article only applies to Atlassian products on the Server and Data Center platforms.

Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible


Problem

When linking dependencies of upstream or downstream between stories, 1 day and due date is automatically populated. 

Diagnosis

Client is using BigPicture - for ppm, project management for resource management

Cause

This is default behavior in BigPicture - for ppm, project management when synchronizing with JIRA.

Workaround

Ensure that all settings are configured for the BigPicture Gantt configuration, and Task period configuration is no synchonizing.

  1. Go to ⚙ > System > BigPicture > Gantt configuration
  2. Ensure all fields are completed
  3. Turn off 'Task period configuration'


Last modified on Jun 12, 2018