Dependencies schedule
Configuring plan settings
On this page
Related content
- No related content found
This feature allow you to have more control on how things are scheduled. Defines how Portfolio's scheduling algorithm can sequence your issues with dependencies.
- Go to
> Scheduling > Scheduling options > Dependency scheduling and select the option you want to apply:
Option 1-Rank dependent work item below required item (Set by default)
Story 1 is blocked by Story 4
This option will make the schedule move Story 1 below Story 4 during scheduling.
The stories between Story 1 and Story 4 will be ranked above Story 4 and Story 1 during scheduling.

Option 2-Rank required work item above dependent item
Story 1 is blocked by Story 4
This option is saying: move Story 4 above Story 1 during scheduling.
All the stories in between Story 1 and Story4 will be ranked above Sa and Sb during scheduling

Option 3-Off
The schedule ignores dependencies and therefore, takes the standard ranking of those items. The dependencies will be still visible in the schedule.

Related topics
Scheduling unestimated items based on default estimates