Using parallel sprints

Still need help?

The Atlassian Community is here for you.

Ask the community

Are you on the right help page?

Using the classic Scrum and Kanban projects? You're in the right place!

Using an Agility project/featured project as part of the new Jira Software? Check out these pages instead.

If you're unsure, check your project menu. If it has the Give feedback and Learn more menu items, you're on an Agility project (aka featured project) and this page isn't for you.



The Parallel sprints feature lets you enable multiple active sprints that are running in parallel with each other. For example, if you have two teams working from the same backlog, each team can now work on their own active sprint simultaneously.

Please note the following caveats when using parallel sprints:

  • The Velocity Chart will not show the velocity per team.
  • The current implementation assumes that the teams perform estimation identically, which is unlikely in practice.

Enabling parallel sprints

  1. Log in as a user with the Administer Jira global permission.
  2. Click your Jira icon ()

     
  3. Click Settings Applications, then scroll down the page to the  Jira Software  section.
  4. Under 

    Jira Software

     configuration
    , select the Parallel Sprints checkbox.

Completing parallel sprints

When completing an active sprint with incomplete issues, you can't directly move these incomplete issues to another active sprint. You need to move these issues to the backlog first, and then you can add the issues to the active sprint.