Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Section
Column

Excerpt Include
Control Chart
nopaneltrue
Control Chart

 To view the control chart:

  1. Include Page
    _RapidBoardNav_instructions
    _RapidBoardNav_instructions

  2. Click Report, then select Control Chart from the drop-down at left. The control chart for your current sprint will be displayed (see screenshot below).
    • Hover over the graph at any point to display actual values of the moving average.
    • By default the chart will select all column(s) other than the first and last (usually the 'To Do' and 'Done' columns). Since the chart shows the average amount of time each issue spent in each of these columns this means that the default chart shows cycle time. To re-draw the chart to show lead time use Refine (as below) and select all columns other than the last
    • To re-draw the chart excluding a column(s) or swimlane(s), or to apply a quick filter, click Refine (see below).
    • To select a different timeframe (past week/past month/past 3 months/past 6 months/all time/custom), click the date range at the top of the chart.

Note that the control chart is

Include Page
_Board
_Board
-specific, that is, it will only include issues which match your
Include Page
_Board
_Board
's Saved Filter.

Column
width240px
Panel

On this page:

Table of Contents

...