Screenshot: Sprint Report (click to enlarge)

Image RemovedImage Added

Please note

  • The Sprint Report is board-specific, that is, it will only include issues which match your board's Saved Filter.
  • The values for each issue's Estimate are recorded at the time the sprint is started. Changing the Estimate value afterwards will not be reflected in the Sprint Report.
  • Issues added after the sprint starts are indicated with an asterisk.
  • For some issues, the Story Points are not shown in the Sprint Report. This is because the Sprint Report shows information initially included in the sprint – that is, what the team actually committed to. (That being said, if you add an issue with zero story points to a sprint, start the sprint and then change the Story Points, you will see the initial value in the Sprint Report.) If you would like to see all changes, switch to the Burndown Chart instead.