Jira Align Estimation Trend Report - Program Estimation Accuracy (Story Points)


Summary

This article explains the calculations for the chart called “Program Estimation Accuracy (Story Points)” in the Estimation Trend (Program Planning Accuracy) report.

Solution

1 - Points Planned (aka Points Committed)

Top-tier configuration bar set to:

  • Program: Program A

  • PI: PI 2

  • Stories have LOE points.

  • All Stories belonging to Program: Program A

Scenario 

PI

Sprint

StoryGrid Export Stories

Estimation Trend Report - Program Estimation Accuracy (Story Points) Chart

Agile Team Stories





If the Story's PI is assigned to PI 2 AND to a sprint that belongs to parent PI 2, then the Story will be included eg Story 1063

PI 2

Belongs to PI 2

Yes

Yes

If the Story's PI is assigned to the PI 2 but no sprint is assigned, then the Story will be included

PI 2

Unassigned Backlog

Yes

Yes

If the Story's Sprint is a sprint that belongs to the parent PI 2, but the PI is "Unassigned Backlog" then the Story will be included. 

Unassigned Backlog

Belongs to PI 2 

 Yes

 Yes

If the Story's Sprint is a sprint that belongs to the parent PI 2, but the assigned PI is not PI 2 then the Story will be included.

Assigned but not PI 2

Belongs to PI 2

Yes

Yes

If the Story's PI is assigned to PI 2 AND a sprint that does NOT belong to the parent PI, then the Story will be included 

PI 2

Assigned but does not belong to PI 2

Yes

Yes

Kanban Team Stories





Kanban Team Stories assigned to the PI 2

 PI 2

 N/A

Yes

Yes

Kanban Team Stories assigned to other PI

 None OR Assigned but not PI 2

N/A 

No

No

Other scenarios





Parent Feature is in a recycled bin.
Child Stories counted

 PI 2

 Belongs to PI 2

Yes

No

Stories with Inactive Teams

 PI 2

 Belongs to PI 2

Yes

Yes 


2- Points Accepted

As above, however, the Story State must be set to “5 - Accepted”