Linked Confluence & Jira Systems display dates off by 1 from each other

robotsnoindex


Platform Notice: Data Center - This article applies to Atlassian products on the Data Center platform.

Note that this knowledge base article was created for the Data Center version of the product. Data Center knowledge base articles for non-Data Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

Dates in Jira and in Confluence have a day's difference from each other across the application link.

Confluence:


Jira:


Environment

Any with an Application Link between Confluence and Jira

Diagnosis

  • There is consistently a difference of one day in date-type information shared between the two systems.
  • Jira and Confluence are configured with different native Time Zones in their Java environments.

Cause

Since the two environments do not share a time zone and the date information is passed between them as just a date, a time zone correction is being applied for the date as it passes between Jira and Confluence. The result is an offset that appears to be showing a different date on each end of the application link. Correcting the time zone difference will make both programs agree on the date.

Solution

Configure both servers to use the same time zone, as in the instructions in our KB article on Setting the timezone for the Java environment.


Last modified on Mar 7, 2025

Was this helpful?

Yes
No
Provide feedback about this article
Powered by Confluence and Scroll Viewport.