The GreenHopper Planning Board allows you to select multiple issues and perform JIRA on them. Bulk Operations enable you to save time by performing the following operations on multiple issues at once:

  • Workflow Transition
  • Delete
  • Move
  • Edit
(info) Note that you will only be able to perform Bulk Operations if you have the 'Bulk Change' , plus appropriate (s) in the relevant project(s).

 

See also:

  •  

 

To modify bulk issues in GreenHopper,

  1. Log into JIRA.
  2. Select your project from the project dropdown in the top navigation bar, if it is not already selected.
  3. Select one or multiple issues (i.e. cards) with your mouse.
  4. Select 'Bulk Change' from the 'Tools' menu.
  5. The JIRA 'Bulk Operations - Step 1' screen will appear. It will display all the issues from your Planning Board, with your chosen issues selected.
  6. Verify that your desired issues are selected, then click the 'Next' button.
  7. On the next screen, choose the Bulk Operation you wish to perform: