The Version Workload Report displays useful time tracking information on the current workload for a specific version within a specific project. For the specified version, it shows a list of unresolved issues assigned to each user, each user's workload, and a summary of the total workload remaining for the version.

Note: this report is only available if time tracking has been enabled by your JIRA administrator.


On this page:

What does the Version Workload report look like?

The report generated will look something like this:

Screenshot: Version Workload Report

The first table summarises the workload for each user, broken down by issue type, for the specified version.

Following the summary, the report is composed of individual sections for each user --- with workload broken down by issue type. Each individual section begins with the workload total for the specific user. Finally, all unassigned issues (if any exist) are displayed.

Generating a Version Workload Report

To generate the report:

  1. Navigate to the desired project.
  2. Choose Summary (tab) > Reports menu > Version Workload Report.
    If you are using JIRA 5.2.1 or later, the reports will be listed in the Reports section on the Summary tab, not in a Reports menu.
  3. In the Version drop-down list, select the version on which you wish to report. The report will include all issues that belong to this version, that is, all issues whose Fix Version is this version.
  4. In the Display unestimated issues drop-down list, choose which issues will be included in the report:
  5. In the Sub-task Inclusion drop-down list (note, this will only appear if sub-tasksare enabled), choose which sub-tasks will be included in the report, for all parent issues that belong to this version:

Note: sub-tasks which belong to this version, but whose parent issues do not belong to this version, will always be included in the report.