Viewing the Epic Burndown
Screenshot: Example Epic Burndown report (story points)
About the Epic Burndown report
The Epic Burndown report shows you how your team is progressing against the work for a epic. An epic is a large user story that can be broken down into a number of smaller stories. The report will show data based on the estimation statistic that your board is using.
Here are some of the ways that you could use an Epic Burndown report:
- See how quickly your team is working through the epic.
- See how work added/removed during the sprint has affected your team's overall progress.
- Predict how many sprints it will take to complete the work for an epic, based on past sprints and changes during the sprints.
If you have used the Epic Report before, you will notice some similarities, however the Epic Burndown is optimised for scrum teams who work in sprints and makes tracking much easier.
On this page:
Viewing the Epic Burndown report
To view the Epic Burndown report:
- Navigate to the desired board.
- Click Reports.
- Select Epic Burndown from the Reports dropdown at the top of the page.
- Choose the desired epic from the dropdown next to the Epic Burndown header. You will be able to choose from epics that are in projects configured for your board (via the board's filter).
Tip: Click How to read this chart at the top of the chart to view a short description of the Epic Burndown report.
If you are using Internet Explorer 8, the Epic Burndown will not work.
Printing the Epic Burndown report
To print the report, view the report and use the print functionality for your browser. The report will fit to either A4 or Letter-sized pages in both portrait and landscape (note, there is a known issue printing in landscape using Chrome).
Understanding the Epic Burndown report
Before you start using the Epic Burndown report, you should get to know how it works.
The sprint bar
- Light green section = work completed during the sprint.
Note, if a bar is completely light green, you won't be able to tell how much of the work completed was originally estimated or not. To find out this information, click the bar to view the details. - Light blue section = work that is remaining in the epic, out of the total work estimated for the epic at the start of the sprint.
- Dark blue section = work that was added during the sprint, but not originally included (i.e. scope change).
- Light green section + light blue section = total work in the epic, that was originally estimated at the start of the sprint.
- Light blue section + dark blue section = total work in the epic, that is remaining at the end of the sprint.
- Bars with grey sections = predicted sprints (see below).
Predicted sprints
Predicted sprints are calculated based on your team's velocity* (amount of work completed in the last three sprints) and the total work remaining for the epic. Scope change is not considered when calculating the velocity*, but is included in the total work remaining.
* not the same as the velocity described in the velocity chart.
Consider the following example :
- Assessing the outstanding work: 12 story points are remaining for the epic, at the start of the current sprint (sprint 10).
- Calculating the velocity: 7 story points were completed in the last three sprints (sprint 8, sprint 9 and sprint 10). This averages out to a velocity of 2 story points per sprint, rounding to nearest story point.
- Predicting the remaining sprints: At a velocity of 2 story points per sprint, it will take 6 more sprints to complete the work for the epic. That is, 6 sprints of 2 story points each.
Other functionality
The following questions and answers cover the other key functionality in the Epic Burndown report:
Known issues
If you encounter an issue that is not on this list, please raise it in our issue tracker.


