Screenshot: Velocity Chart (click to enlarge) The velocity can be estimated as the average, over several recent sprints, of the sum of the estimates for the amount of work completed by a team per sprint — so in the chart above, the velocity = (37 + 47 + 50 +57) / 4 = 48. A team's recent velocity can be useful in helping to predict how much work can be completed by the team in a future sprint.