Documentation for GreenHopper 6.2.x. Documentation for earlier versions of GreenHopper is [available too].

You can filter out weekends, holidays, and other times during which your team might not be working on your board's project(s).

To specify working days,

  1. Select Agile > Manage Boards from the top navigation bar, then click the Configure link corresponding to the board of interest.

    (info) Note that only the owner of a board (or a person with the 'JIRA Administrators' global permission) can configure a board.
  2. Click the Working Days tab.
  3. If your team has a different time zone to the server, select the team's Time Zone.

  4. In Standard Working Days, select all the weekdays on which your team typically works.

  5. In Non-Working Days, click Add Date to specify holidays or one-off dates on which your team will not be working.
    (info) To remove a Non-Working Day, click the 'x' next to the date (see screenshot below).

These settings will be reflected in your Burndown Chart, Control Chart and Version Report.

Screenshot 1: the 'Board Configuration' screen — 'Working Days' tab

 

 

3 Comments

  1. Daniel Serodio

    Shouldn't this setting also affect the "Days remaining" widget?

    1. At this time, the Days Remaining Gadget is only available for the Classic boards, whereas this setting applies to the new boards.

  2. Martin

    The new board's Days Remaining Gadget will be available in the next release of GreenHopper and does take into account non-working days.