Dependencies report

Still need help?

The Atlassian Community is here for you.

Ask the community

This page discusses the usage of Advanced Roadmaps live plans. If you're using the redesigned planning interface, see this page instead.

You can use the dependencies report to see the dependencies (both scheduled and unscheduled) that the work items in your plan may have. This is handy in mitigating any possible project delays, as well as facilitating risk management processes efficiently.

When it comes to dependencies in plans, an issue that has a dependent issue is considered the required work item.

For example, let's say:

  • you have these issues: CPU-309 and CPU-310,
  • and CPU-310 is needed by CPU-309

In this example, work for CPU-309 won't start until work for CPU-310 is completed. So, CPU-310 is the required work item, while CPU-309 is the dependent work item.

Keeping the concept of required and dependent work items in mind, the dependencies report contains the following information:

Issue details

This includes the following for both required and dependent work items:

  • issue key
  • issue summary
  • issue type
StatusThe status of both required and dependent work items
Scheduled end dateThe scheduled end date of the required work item
Scheduled start dateThe scheduled start date of the dependent work item

Note the following details:

  • The Dependency column in the report shows the relationship between dependent work items and required work items, indicating that the required work item blocks the dependent work item.
  • If a required work item has two dependent work items, each dependent work item appears in its own individual row.

To view the dependencies report of a plan:

  1. In your plan, click the Reports tab to display the reports section for your plan.
  2. Click the switch report menu > Dependencies.

Note the following details:

  • You can filter the details of the dependencies report by projects, releases, teams, status, completion date, scheduled range, and themes.
  • You can also sort the details by:
    • required work items — issue key, scheduled end date, and status
    • dependent work items — issue key, scheduled start date, and status