[Bamboo Knowledge Base]
There may be times when you want to prevent a failing test from causing the whole build to fail.
Possible scenarios where this may be useful include:
In Bamboo, you can temporarily disconnect any test's results from the plan build results by quarantining the test. The test is still run whenever the plan is built, but the test's results do not affect the plan's build results.
You can always restore a test's results to the build results when required, for example if the test is now passing.
All the quarantined tests for a plan are displayed on the Quarantined Tests tab of the plan summary. The status bar for each test shows the recent build history of the test.
You need plan administrator permission to quarantine a test.
You need plan administrator permission to restore a test.
Screenshot: The quarantined tests for a plan, showing the Status bar.