Problem
Unable to update the project lead
- Clicked the 'Update' button, nothing happened and no any error message.
- The loading circle occurs very shortly but it just stay on the same popup page.
Diagnosis
Environment
- Upgraded from JIRA 6.x to JIRA 7
Diagnostic Steps
- Go to JIRA Administration > Projects > Select Project > Edit Project
- Verify the project name character counts
Cause
This is a bug caused by the introduction of the project length name limit < 20 characters
- If there is projects which holds project name with >20 characters, when migrated, you wont be able to edit the project lead
Workaround
Rename the project name accordingly to <20 characters
Resolution
Go to Settings (cog icon on top right) > System > Maximum project name size and increase the maximum allowed characters here.