Configuring team settings

On this page

Still need help?

The Atlassian Community is here for you.

Ask the community

You can configure the scheduling methodology, and the velocity or the weekly capacity of the teams associated with your plan.

Configuring the scheduling methodology of a team:

  1. Go to your plan via Portfolio (in header) > View Portfolio > click your plan.
  2. Click the Teams tab to display the teams section below the timeline.
  3. In the Teams section, find the team whose settings you want to configure, then expand the team to view its details.
  4. From the upper-right section of the selected team, click the scheduling methodology menu.
  5. Select from one of the following methodology options:
    • Scrum, if the team works in sprints or fixed iterations, then specify the number of weeks that comprise a sprint. If you want to define the default value for your sprints, see Configuring scheduling settings.
    • Kanban, if the team works in a continuous schedule.
      (info) If your plan uses story points for estimation, the Kanban option won't be available. See Configuring scheduling settings to know more about changing the planning unit of your plan.
  6. Commit the changes back to your Jira instance.

Configuring team velocity

If you're using story points for estimation, you will see the following details about your team:

1Team velocity
  • The number of story points the team completes in each sprint.
  • You can set a value for team velocity if needed.
2Forecasted velocity

The team velocity that's forecasted for the next few sprints, based on:

  • the team's performance over past sprints
  • the availability of your team members
3Past velocity
  • The team velocity over past sprints in gray bars, and the suggested velocity for the next sprint in a blue bar.
  • You can choose to use the suggested velocity, if it's a realistic value for your team.
  • To see past velocity, the issue source of your team must be a Jira board.

Configuring weekly capacity

If you're using time-based estimates, the weekly capacity of your team is the total sum of the weekly hours of each team member. You can configure the weekly hours of each member in your team, to get your team's overall weekly capacity.

To configure weekly hours of a team member:

  1. In the Teams section, from the Weekly hours column, click the row of the team member whose hours you want to configure.
  2. Enter the weekly hours for the member.
  3.  Commit the changes back to your Jira instance.

Related topics

Last modified on Sep 6, 2018

Was this helpful?

Yes
No
Provide feedback about this article
Powered by Confluence and Scroll Viewport.