Editing multiple issues in bulk
You can assign a specific value to or remove a specific value from multiple issues. This way, you don't have to make the same change for several issues over and over again.
Available bulk actions
You can perform the following bulk actions:
- Assign issues to an assignee
- Assign issues to a team
- Update the parent of issues
- Update the release of issues
- Update the sprint of issues
- Update the target dates of issues
- Remove issues from a plan
- You need the Portfolio for Jira user permission to save changes in Jira.
Sub-tasks inherit certain values of its parent story, including sprints, releases, and teams. You'll need to update such values of the parent story instead.
Assigning issues to an assignee
This section applies to issues that have never been assigned to an assignee, or issues that you want to reassign to a different assignee.
- In the scope section, select the checkboxes for the corresponding issues.
- Click the Bulk actions menu > Assignee. The Bulk actions dialog will be displayed.
- Choose the corresponding assignee for the selected issues.
To remove the current assignees for the selected issues, choose Unassigned instead. - Click Apply. The issues will be assigned to the selected assignee.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the assignee changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Assigning issues to a team
This section applies to issues that have never been assigned to a team, or issues that you want to reassign to a different team.
- In the scope section, select the checkboxes for the corresponding issues.
- Click the Bulk actions menu > Team. The Bulk actions dialog will be displayed.
- Choose the corresponding team for the selected issues.To remove the current values for the selected issues, choose None instead.
- Click Apply. The issues will be assigned to the selected team.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the team changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Updating the parent of issues
To update the parent of issues, the issues must be of the same hierarchy level. Also, issues of the highest level in the hierarchy can't be moved to a new parent since these issues can't be moved any higher.
- In the scope section, select the checkboxes for corresponding issues.
- Click the Bulk actions menu > Parent. The Bulk actions dialog will be displayed.
- Choose the corresponding parent for the selected issues.To remove the current values for the selected issues, choose None instead.
- Click Apply. The issues will be moved to the selected parent.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the parent changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Updating the release of issues
To update the release of multiple issues, the issues must belong to the same project.
- In the scope section, select the checkboxes for the corresponding issues.
- Click the Bulk actions menu > Release. The Bulk actions dialog will be displayed.
- Choose the corresponding release for the selected issues.To remove the current values for the selected issues, choose None instead.
- Click Apply. The issues will be added to the selected release.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the release changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Updating the sprint of issues
In the scope section, select the checkboxes for corresponding issues.
- Click the Bulk actions menu > Sprint. The Bulk actions dialog will be displayed.
- Choose the corresponding sprint for the selected issues.To remove the current values for the selected issues, choose None instead.
- Click Apply. The issues will be moved to the selected sprint.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the sprint changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Updating the target dates of issues
- In the scope section, select the checkboxes for the corresponding issues.
- To update the target start date of issues:
- Click the Bulk actions menu > Target start. The Bulk actions dialog will be displayed.
- Choose the corresponding target start date for the selected issues.To remove the current values for the selected issues, choose None instead.
- To update the target end date of issues:
- Click the Bulk actions menu > Target end. The Bulk actions dialog will be displayed.
- Choose the corresponding target end date for the selected issues.To remove the current values for the selected issues, choose None instead.
- Click Apply. The dates will be updated for the issues.
Note that the issues will remain selected in the scope section. - Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the target date changes are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
Removing issues from a plan
- In the scope section, select the checkboxes for the corresponding issues.
- Click the Bulk actions menu > Remove from plan.
- In the confirmation dialog, click Remove.
- Save the changes by doing the following:
- Click Review changes. The 'Review changes' dialog will display, with all changes selected by default.
- Make sure the checkboxes for the issues you want to remove are selected, then click Save selected changes in Jira.
You need the Portfolio for Jira user permission to save changes in Jira.
- Issues that are already saved in Jira will be removed from the plan, but will remain in Jira.
- Issues that aren't saved in Jira just yet will be permanently deleted from the plan.