Project and Risk Score Value Calculations for Program Increment Status Report - Jira Align

Still need help?

The Atlassian Community is here for you.

Ask the community


Summary

The Program Increment Status Report includes a Project Score and Risk Score calculation that is based on word values rather than numeric values and it is important for the customer to be able to understand just what degree of separation we are seeing with a Low/Medium/High/Etc option.

Environment

Jira Align

Solution

The Risk Score is calculated based on the following Word to Number of conversions from the Spend Risk section of the Spend tab for any given Epic


Field

Text Value

Numeric Value for Score Calculation

Business Impact

High

0


Medium High

2


Medium

3


Low

6




Risk Appetite

Low

0


Moderate

2


High

3


Extreme

4




IT Risk

High

0


Medium

4


Low

9


Unknown

4


Disagreement on Risk

4




Failure Impact

Negligible

9


Minor

4


Moderate

2


Significant

1


Severe

0




Failure Probability

1%-20%

8


21%-40%

6


41% - 60%

4


61%-80%

3


81%-100%

0


The Project Score is calculated based on the following Word to Number conversions from the Program Increment Project/Alignment Scoring Tab on any given PI

Field

Text Value

Numeric Value

Cost / Time To Market / Development Risk

Low

8


Medium

4


High

0




Profit Potential

Low

0


Medium

4


High

8






Last modified on Feb 23, 2024