Advanced Roadmap| How to re-include "Removed issues" in the Timeline view

Still need help?

The Atlassian Community is here for you.

Ask the community

Platform Notice: Cloud - This article applies to Atlassian products on the cloud platform.

Summary

This Kb describes the steps to reinclude the Jira issues that have been removed from the timeline of roadmap previously.

Environment

Jira cloud

Solution: 

The steps to perform this activity are:

  1. Navigate to the Advanced Roadmaps Plan  
  2. Click on the Plan settings
  3. Click on the Removed issues tab under the Source data section
  4. Select any issue and re-include them in the timeline.

Here is a video recording for reference:

 AR_removed Issue.mp4

Note

Please note: If the issues in the "Removed issues" page are high then you may have latency issues.

To avoid this issue, you can opt for either one of these options:

  1. Add the issues back to the PLAN by re-including them.
    (Or)
  2. Create a fresh plan with better filtered issue sources, by having a filter that specifically describes the issues that are required. 

Last modified on Sep 28, 2023