Problem

In Releases tab, user will see a red box like this:

Cause

The Release End Date should not be less than the sprint's end date. In the above example, the sprint is set to one week, and the Release End Date is configured to a date before the sprint's completion date.

Resolution

Set the Release End Date to a date on / after the sprint's completion date