Platform notice: Server and Data Center only. This article only applies to Atlassian products on the Server and Data Center platforms.
Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.
*Except Fisheye and Crucible
Problem
In Releases tab, user will see a red box like this:
Cause
The Release End Date should not be less than the sprint's end date. In the above example, the sprint is set to one week, and the Release End Date is configured to a date before the sprint's completion date.
Resolution
Set the Release End Date to a date on / after the sprint's completion date