The Releases view provides you with a summary of releases and iterations for teams using a Scrum schedule. You can access the releases report view by following these instructions:

  1. Select your plan and go to Reports > Releases. 
  2. Change the release view by selecting  and changing the granularity filters.
  • Releases
    • Release name, date and type.
    • Planned Capacity: Total number of days, hours or story points planned for a release depending on your planning unit (see Settings).
  • Sprints - (Only available for teams working on an iteration-based schedule)
    • Sprint name and date.
    • Planned capacity: The total number of days, hours or story points planned for a release depending on your planning unit, (see Settings).
    • Free capacity: The total number of days, hours or story points that would still be available during the release period, if all resources could be booked up to 100%.