The search and filtering controls in the plan view allow you to quickly narrow the plan content and timeline to selected items, releases, and teams.
Filter name | Description |
---|---|
Epic | Allows you to change the hierarchy level shown in the scope. |
Project | Filter by projects that work items originated from. |
Releases | Filter by the releases that work items were assigned to. |
Teams | Filter by the teams that work items were assigned to. |
Contains text | Filter by work item title text. Parents of matched items will also be displayed. |
Status | Filter by Jira application issue status. Open issues can be displayed, or both open and closed issues.
|
Completion date | When it is not set, it will show the completed issues since the beginning of the active sprint. If there aren't active sprints on the linked data sources, no completed issues will show up unless we explicitly set this filter.
|
Schedule range |
|
Themes | Filter the timeline by theme. |
Note
For the projects, releases and date range, the filter considers values chosen by the user as well as values calculated by the algorithm.
Example:
If you manually assign issue A to team Foo and the algorithm automatically assigned issue B to team Foo; filtering by team Foo would return issues A and B.