Target schedule report
The target schedule report is a view of your plan's schedule that visualizes the baselines set by adding target start and target due date dates to your issues. The baselines shown on the target schedule allow you to track your plan over time and compare the current plan status with the originally planned schedule.
View the target schedule report
You'll only see target date markers if you have set target start and end dates on the issues at the hierarchy level you're currently viewing the report at. For example, if you're viewing the report at the initiative level but don't have target dates set on any initiatives, you won't see any target date markers. Learn more about adding target start and target due date.
- Go to your plan via Portfolio > click your plan.
- Click the Reports tab to display the reports section of your plan.
- Click the switch report menu > Target schedule.
You can filter the information displayed in the report by hierarchy level, projects, releases, teams and so forth using the hierarchy level filter or the global filters.
Configure the target schedule report
You can configure the following display settings for the target schedule report.
Go to your plan via Portfolio > click your plan.
Click the Reports tab to display the reports section of your plan.
- Select to open the report settings and select the filters you want to apply.
Report setting | Description | Setting option |
---|---|---|
Line | Defines how work items are visualized. |
|
Coloring | Lets you either visualize all the work items in your plan with a single color (this can be configured) or multiple colors to match the themes each work item is associated with. |
|
Zoom | Lets you zoom in and out. |
|
Show | Lets you specify whether certain information is presented on your schedule or not. |
|